Communiquez avec les autres et partagez vos connaissances professionnelles

Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.

Suivre

A project manager believes that modifying the scope of the project may provide added value for the customer. The project manager should?

 

A. Change the project's objectives

B. Call a meeting of the configuration control board

C. Postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline

D. Change the scope baseline

E. Prepare a variance report

 

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2017/02/11
Muhammad Farooq
par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

C. Postpone the modification until a separate enhancement project is funded after this project is completed according to the original baseline

Krishna   KHASANIS  PMP
par Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

In my opinion appropriate choice shall be to change the scope baseline after consulting with stakeholders , project ream & customer.

B. Call a meeting of the configuration control board

DR MD ANWAR HOSSAIN
par DR MD ANWAR HOSSAIN , Moderator , bayt.com

Thank you for invitation. I seem option B. Call a meeting of the configuration control board is good answer.