Planning activities such that predetermined resource availability pools are not exceeded is called?

A. Manpower planning.

B. Manpower leveling.

C. Resource leveling.

D. Manpower contingency planning.

E. Resource limited planning.

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2017/02/11
Jacob P
par Jacob P , IT Project Management Consultant , Eickhoff Wind Asia Pvt Ltd

C. Resource leveling (as per PMBOK5)

Sattar Abdulkarim  Mohamed
par Sattar Abdulkarim Mohamed , Country Sales Director , Ideal Technical Solutions

Apprciation for your invitation. My answer is Option E - Resource Limited Planning.

Mohamed Kamal
par Mohamed Kamal , Cost Control Manager , China State Construction Engineering Corporation Ltd. (Egypt)

C.Resource Leveling most fits your question