By which process may an unsuccessful supplier seek remedy for unjust awards?

 A. None of the other alternatives apply

B. Contract dispute

 C. Bid protest

D. Coffective action

 E. Stop work order

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2017/02/11
Krishna   KHASANIS  PMP
par Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

Bid Protest is a process in which an unsuccessful supplier takes objections to unjust contract awards.

Md Fazlur Rahman
par Md Fazlur Rahman , Procurement Specialist , Engineering and Planning Consultants Ltd

Since the supplier is unsuccessful, he could go for (C). Bid protest

Nadeem Asghar
par Nadeem Asghar , Supply Chain Consultant/Trainer , Independent Practitioner

Bid Protest Option C is the most relevant

Sattar Abdulkarim  Mohamed
par Sattar Abdulkarim Mohamed , Country Sales Director , Ideal Technical Solutions

Appreciation for the invitation. My answer is Option-A.