Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.
A. Both1) rearranging conflicting tasks, and2) showing the outer dependencies of tasks
B. showing the outer dependencies of tasks
C. depicting actual versus planned tasks
D. rearranging conflicting tasks
It is C - depicting actual versus planned tasks .
A Gantt Chart provides a graphical illustration of a schedule that helps to plan, coordinate, and track specific tasks in a project. So it matches with your C option.
Thank you for invitation. I seem C. depicting actual versus planned tasks is good answer.
B. showing the outer dependencies of tasks