Communiquez avec les autres et partagez vos connaissances professionnelles

Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.

Suivre

Describe how you deal with provisional items during construction phase?

during construction some vital problems may arise here and there which need small site meeting to decide upon and move further.

user-image
Question ajoutée par Salah Abdel Ghafar Ibrahim Abdel Rhman Al- Saada , Senior Project Engineer , Qatar Project Management[QPM]
Date de publication: 2013/10/05
Teodor Pop
par Teodor Pop , BIM Manager , ISG jv

For the main Contractor it is important that all the provisional items are clearly described and instructed. Quite often these are used for the architectural finishes.

It is recommended that each party agree as much as possible early during the contract on the detail for Provisional Sum works, including how the works are to be included in the programme. Any assumption and qualification in relation to the relevant works should be clearly documented so that any departure from what was agreed can be clearly identified and corrected.

robiul islam
par robiul islam , Procurement and warehouse manager , Aollaa company

First need to talk with site supervisir and also department head, then can be get a correct solution about the deal

More Questions Like This