The cost of corrective action taken by the purchaser and chargeable to the supplier under the terms of the contract is?

 

A. Bid cost considerations

B. None of the other alternatives apply

C. Back charge

D. Payment authorization

E. Release payment

 

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2017/02/24
Hussain  Alshagrawi
par Hussain Alshagrawi , Freelancer Consultant , Freelancer

Yes, it would be Back Charge;C

DR MD ANWAR HOSSAIN
par DR MD ANWAR HOSSAIN , Moderator , bayt.com

Thank you. The answer may be C. Back charge

Krishna   KHASANIS  PMP
par Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

I think it is C - Back Charge

hisham abu dagga
par hisham abu dagga , Project Manager / مدير مشاريع , مؤسسة عبدالكريم العواض للمقاولات

 

Thank you for the invitation

Option C

Abdul Rehman
par Abdul Rehman , Electrical Engineer , Tamdeed Projects

Thank you for the invitation. My answer is C