Start networking and exchanging professional insights

Register now or log in to join your professional community.

Follow

The project manager must be concerned with building a closely knit team. During the project kickoff meeting, the project manager can get a?

good start at team building by providing the team with:

A. Proposed salary increases if the project is successful

B. Linear responsibility charts

C. A promise of future assignments

D. Bonuses for early completion date

E. Well-defined project objectives

user-image
Question added by Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date Posted: 2017/03/24
DR MD ANWAR HOSSAIN
by DR MD ANWAR HOSSAIN , Moderator , bayt.com

Thank you. I think proper answer is E. Well-defined project objectives.

Sattar Abdulkarim  Mohamed
by Sattar Abdulkarim Mohamed , Country Sales Director , Ideal Technical Solutions

The correct answer is Option E - Well-defined project objectives.

Obaid ur Rehman
by Obaid ur Rehman , HR Executive , Al Bahr Al Arabi Marine Engineering Services

Well-defined project objectives with Bonuses for early completion date.

Sadeq Al-Abbad
by Sadeq Al-Abbad , Performance Development Coordinator , HALLIBURTON Energy Services

l agree with option E thanks for invitation

SYED SHAIKH ABEL ALQUDSI
by SYED SHAIKH ABEL ALQUDSI , Safety Manager , EMAS Marine Off-shore Services

the planning up to the confirmation of actions to be taken stage by his team.

Krishna   KHASANIS  PMP
by Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

Of course it is option E since it is kick off meeting & thanks for the invitation.

hisham abu dagga
by hisham abu dagga , Project Manager / مدير مشاريع , مؤسسة عبدالكريم العواض للمقاولات

 

Thank you for the invitation

Thanks for the information 

 

I Agree Option E

More Questions Like This