You have your activity list in hand and several alternative time estimates for each activity and are ready to diagram the activity dependencies. You should use which of the following?
A. PDM techniques
B. ADM techniques
C. PDM or ADM techniques
D. AON techniques
Today most network diagrams are created using option A - PDM technique.
In my opinion - B. ADM techniques
Thank you for the invitation
Thanks for the information
I Agree Option B
Thank you. Option C. PDM or ADM techniques.
--------- Option A. PDM techniques -------