Scheduling is the process by which decisions are made concerning?

A. Tasks to be accomplished.

B. Both1)Tasks to be accomplished and2) Time when the tasks are to be completed.

C. All of the other alternatives apply.

D. Time when the tasks are to be completed.

E. Personnel/organization that will be assigned to accomplish the task.

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2017/03/24
Majid Kubba
par Majid Kubba , Oil & Gas Site Construction Manager, Project Management,Operation Manager,P6 Planner . QA/QC civil , kubba gruop.جنة الخليج للمقاوﻻت. الكاف للمقاولات. البان تكريت والبصرة. شركةريستراتا البريطانية

Many thanks

the answer is - Option B.

Best Regards.

يوسف دمدوم
par يوسف دمدوم , مهندس و مسير , مقاولة اشغال البناء

Thank you for the invitation

i agree the option B

Krishna   KHASANIS  PMP
par Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

Mr.Muhammad is right , scheduling concerns itself with as mentioned in option B - Tasks & Timings of the tasks to be accomplished .

Option D. Time when the tasks are to be completed

Muhammad Farooq
par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

In my opinion

B. Both1)Tasks to be accomplished and2) Time when the tasks are to be completed.

hisham abu dagga
par hisham abu dagga , Project Manager / مدير مشاريع , مؤسسة عبدالكريم العواض للمقاولات

 

Thank you for the invitation

Thanks for the information 

 

I Agree Option B

Abdul Rehman
par Abdul Rehman , Electrical Engineer , Tamdeed Projects

Thanks, my answer is option D

DR MD ANWAR HOSSAIN
par DR MD ANWAR HOSSAIN , Moderator , bayt.com

Thank you option D is good answer.