Which does not create changes to the Project Scope Statement or Work Breakdown Structure?

 

A. Estimate Activity Durations

B. Sequence Activities

C. Define Activities

D. Estimate Activity Resources

 

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2017/03/31
Javad Taghavi
par Javad Taghavi , Program Manager, Senior Adviser in Project Management , KCE Co.

in my point of view the right item should be C-Define Activities.

Because, all 4 process directly or indirectly related to pss or wbs, but only "define activities" is not allowed to update project documents, it means in this process only work packages in wbs will be decomposed not more not less. but other process with considering concept of process and activities allowed to change in project documents especially their input documents.

 

hisham abu dagga
par hisham abu dagga , Project Manager / مدير مشاريع , مؤسسة عبدالكريم العواض للمقاولات

Thank you for the invitation

Thanks for the information

 

Option A

Krishna   KHASANIS  PMP
par Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

Action of " Estimating activity resources " normally does not affect the project scope or wbs.

Abdul Rehman
par Abdul Rehman , Electrical Engineer , Tamdeed Projects

Sorry, I have no clue here.

Muhammad Farooq
par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

In my opinion optionA -------------------

DR MD ANWAR HOSSAIN
par DR MD ANWAR HOSSAIN , Moderator , bayt.com

Thank you for invitation. I think appropriate answer is C. Define Activities.

------------- C. Define Activities -------------