element in the WBS is% higher than previous project for very similar work. What should you do next?
A. Accept the estimate
B. Reduce the estimate
C. Ask the person responsible about the difference
D. Ignore it
(C)
to ask the responsible person of the estimate if he has logical reason for the raise
If i am the project manager then i will follow below steps :
1. Ask the person responsible about the difference
2.Get Estimate , Reduce the estimate
3. Accept the estimate
It is more convenient answer Option C - Ask the Person Responsible about the Difference.
Thank you for invitation. I think C. Developing project schedule with contingency reserves as a recognition of the schedule risk.
C. Ask the person responsible about the difference
Option - C is most appropriate action to be taken under the circumstances.
you should analysis and as the responsible emp.
Indeed C.: Ask the person responsible about the difference and try to analyse why it happened