You are a project manager for Star Light Strings. Star Light manufactures strings of lights for outdoor display. Its products range from simple?

light strings to elaborate lights with animal designs, bug designs, memorabilia, and so on. Your newest project requires a change. One of the business unit managers submitted a change through the change control system, which utilizes a CCB. Which of the following is true regarding the CCB?

A. The CCB requires all change requests in writing.

B. The CCB approves or denies change requests.

C. The CCB describes how change requests are managed.

D. The CCB requires updates to the appropriate management plan.

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2017/04/07
Krishna   KHASANIS  PMP
par Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

In my opinion option - B is most appropriate & thanks for the invite.

DR MD ANWAR HOSSAIN
par DR MD ANWAR HOSSAIN , Moderator , bayt.com

Thank you. I think answer is B. The CCB approves or denies change requests..

B. The CCB approves or denies change requests