The primary function of the Closing processes is to perform which of the following?

 

A. Perform post-implementation audits to document project successes and failures.

B. Formalize project completion and disseminate this information to project participants.

C. Perform audits to verify the project results against the project requirements.

D. Formalize lessons learned and distribute this information to project participants.

 

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2017/04/07
Abdul Rehman
par Abdul Rehman , Electrical Engineer , Tamdeed Projects

Thanks for the invitation. My answer is B

Krishna   KHASANIS  PMP
par Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

In my opinion option - C is most appropriate.

DR MD ANWAR HOSSAIN
par DR MD ANWAR HOSSAIN , Moderator , bayt.com

Thank you. My answer is option B.

hisham abu dagga
par hisham abu dagga , Project Manager / مدير مشاريع , مؤسسة عبدالكريم العواض للمقاولات

 

Thank you for the invitation

Thanks for the information 

 

I Agree Option B

B. Formalize project completion and disseminate this information to project participants