Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.
A. Cost baseline
B. Critical path
C. Gantt
D. Schedule baseline
The correct answer is cost baseline
On S-Curve you can display cost, physical progress, manhours etc. However based on the question I will vote for A. Cost Baseline.
Thank you for the invitation, I believe the answer is A.
S curve is not a constant. sure there is one at the beginning of the project as constructed from the cost baseline, later it will be reconstructed and compared to the initial one to identify, compare and take corrective measures to control your project performance. Every month the S curve will slightly change its shape.
Thanks
Thank you for the invitation
Iagree the option A
Thanks for the invitation. Sorry, I have no knowledge about it.
Thank you. I seem option A-Cost baseline is a good answer.
Thank you for the invitation
Thanks for the information
I Agree Option A