Communiquez avec les autres et partagez vos connaissances professionnelles

Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.

Suivre

The critical path in a network is the path that?

A. Must be completed before all other paths.

B. All of the other alternatives apply.

C. Will elongate the project if the activities on this path take longer than anticipated.

D. Has the greatest degree of risk.

E. Has the greatest degree of risk and will elongate the project if the activities on this path take

longer than anticipated

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2017/04/20
ZULFIQAR ALI
par ZULFIQAR ALI , Planning/ Project Control Manager , King Abdullah University Of Science And Technology

Critical path is the sequential activities from start to the end of a project. 

My answer is 

C. Will elongate the project if the activities on this path take longer than anticipated.

Zaferullah Sharief, PMP®
par Zaferullah Sharief, PMP® , Project Manager , Huawei Technologies

Option C is the right choice

Vladimir Ivanov
par Vladimir Ivanov , Senior Expert of project planning and project controls (Primavera P6) , SIBUR, Group of companies

F. Is the longest continuous path of the project

Krishna   KHASANIS  PMP
par Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

In my opinion option - C is most appropriate and thanks for the invite.

Muhammad Farooq
par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

C. Will elongate the project if the activities on this path take longer than anticipated

DR MD ANWAR HOSSAIN
par DR MD ANWAR HOSSAIN , Moderator , bayt.com

Thank you. I seem Option D. Has the greatest degree of risk is good answer.

E. Has the greatest degree of risk and will elongate the project if the activities on this path take

longer than anticipated

More Questions Like This