If you are project manager, After a change request has been denied, you should?

A. Forget it

B. Record it and save it.

C. None of the other alternatives apply

D. Pass on to the project team.

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2017/04/20
Krishna   KHASANIS  PMP
par Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

Option - B , denied change request/s should be recorded & saved for future reference purpose.

Zaferullah Sharief, PMP®
par Zaferullah Sharief, PMP® , Project Manager , Huawei Technologies

All the rejected change request should be recorded and file/save it.  So the Option B is the correct choice.