to prospective clients. You will do which of the following at your next stakeholder project status meeting?
A. Report on the progress of the demo, and note that it's a completed task.
B. Preview the demo for stakeholders, and obtain their approval and sign-off.
C. Review the technical documentation of the demo, and obtain approval and sign-off.
D. Report that the demo has been noted as a completed task in the information retrieval system.
B. is the correct answer. Preview the demo
In my opinion
A. Report on the progress of the demo, and note that it's a completed task
I prefer to with option - B and thanks for the invite.
My answer is Option B which is more convenient to get approval and satisfaction of the stakeholders.
B. Preview the demo for stakeholders, and obtain their approval and sign-off.