The two closing procedures are called?

 

A. Contract close out and Verify Scope

B. Project closure and lessons learned

C. Contract close out and administrative closure

D. Project closure and product verification

 

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2017/04/28
Krishna   KHASANIS  PMP
par Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

It is option C - Contarct closeout & Administrative closure & thanks for the invite.

Zaferullah Sharief, PMP®
par Zaferullah Sharief, PMP® , Project Manager , Huawei Technologies

Option C is the right choice

C. Contract close out and administrative closure --------

Muhammad Farooq
par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

In my opinion

C. Contract close out and administrative closure