A. Cannot be related to cost estimates.
B. does not show activity interrelationships.
C. Cannot be related to calendar dates.
D. Cannot be related to manpower planning.
E. Lack of time-phasing.
Option B is the right choice
B. does not show activity interrelationships
Thank you. My option is B. does not show activity interrelationships.
The main disadvantage of bar chart is:
It can't show activity sequencing like lead and lag