Communiquez avec les autres et partagez vos connaissances professionnelles

Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.

Suivre

A negative cost variance and positive schedule variance means?

 

A. The project is over budget and behind schedule

B. The project is under budget and ahead of schedule

C. None of the other alternatives apply.

D. The project will be overrun but ahead of schedule at completion

E. The project is over budget and ahead of schedule

 

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2017/05/05
Zaferullah Sharief, PMP®
par Zaferullah Sharief, PMP® , Project Manager , Huawei Technologies

Option E is the correct choice.

MICHAIL KOSTOUROS  PMP PMI-RMP
par MICHAIL KOSTOUROS PMP PMI-RMP , Project Manager , SEEC S.A.

Negative cost variance means that we spend more than the amount of money we earn, so we are over budget, positive schedule variance means that we earn more than we plant, so we are ahead of schedule. The correct answer is E. 

Sattar Abdulkarim  Mohamed
par Sattar Abdulkarim Mohamed , Country Sales Director , Ideal Technical Solutions

The Correct Answer Option E - The Project Over Budget & Ahead of Schedule.

E. The project is over budget and ahead of schedule

hisham abu dagga
par hisham abu dagga , Project Manager / مدير مشاريع , مؤسسة عبدالكريم العواض للمقاولات

Thanks for invitation

 I Agree answers Option E 

Arvind Arya
par Arvind Arya , Additional Chief Engineer , Ajmer Development Authority

Cost Variance (CV) is a very important factor to measure project performance. CV indicates how much over - or under-budget the project is. CV can be calculated using the following formula: Cost Variance (CV) = Earned Value (EV) − Actual Cost(AC) OR Cost Variance (CV) = it is the difference between budgeted cost of work performed, or BCWP, and the actual cost of work performed, or ACWP (BCWP – ACWP)

Negative variance, meaning losses and shortfalls. A positive schedule variance means the project is ahead of schedule, while a negative schedule variance means that a project is behind schedule

So Answer “ E” is correct.

More Questions Like This