Communiquez avec les autres et partagez vos connaissances professionnelles

Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.

Suivre

What is the primary purpose of a milestone chart?

 

A. To show significant events in the project such as completion of key deliverables.

B. To show resource constraints.

C. To show task dependencies.

D. To highlight the critical path.

 

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2017/05/12
يوسف دمدوم
par يوسف دمدوم , مهندس و مسير , مقاولة اشغال البناء

Thank you for the invitation

I agree the option -A

Zaferullah Sharief, PMP®
par Zaferullah Sharief, PMP® , Project Manager , Huawei Technologies

Option A is the right choice.

A. To show significant events in the project such as completion of key deliverables

Fraz Ali
par Fraz Ali , HSE Engineer , AAA Partnership Pvt. Ltd.

Thanks for invitation. my choice for the subject is Opt (A). To show significant events in the project such as completion of key deliverables.

Mohamed Kamal
par Mohamed Kamal , Cost Control Manager , China State Construction Engineering Corporation Ltd. (Egypt)

option (A) for highlighting important events

Krishna   KHASANIS  PMP
par Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

Of course it is option - A which is most appropriate & thanks for the invite.

Sattar Abdulkarim  Mohamed
par Sattar Abdulkarim Mohamed , Country Sales Director , Ideal Technical Solutions

The Correct answer is Option A - To show significant events in the project such as completion of the key deliverables.

hisham abu dagga
par hisham abu dagga , Project Manager / مدير مشاريع , مؤسسة عبدالكريم العواض للمقاولات

________Thank you for the invitation

Agreed with Option A_________ 

More Questions Like This

Avez-vous besoin d'aide pour créer un CV ayant les mots-clés recherchés par les employeurs?