Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.
A. All of the other alternatives apply.
B.1) a relationship of the uncertainty of critical path activities and2) an indicator of project end
date target confidence
C. an indicator of project end date target confidence
D. a relationship of the uncertainty of critical path activities.
E. a function of critical path, leveling and project costs.
B.1) a relationship of the uncertainty of critical path activities and2) an indicator of project end date target confidence
Option B is the correct answer.
Thanks for the invitation. My answer is B
Thank you for the invitation
I agree the option E