You are the project manager for a large construction project. The project objective is to construct a set of outbuildings to house the Olympic?

support team that will be arriving in your city months from the project start date. Resources are not readily available because they are currently assigned to other projects. Jack, an expert crane operator, is needed for this project two months from today. Which of the following skills will you use to get Jack assigned to your project?

A. Communication skills

B. Problem-solving skills

C. Negotiation and influencing skills

D. Communication and organizational skills

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2017/05/26
Aneesh Shandilya
par Aneesh Shandilya , Manager/ Lead Electrical , Orpic

Option C - negotiation and influencing skills are required to get Jack released from present assignment and deputation to your project.

Sattar Abdulkarim  Mohamed
par Sattar Abdulkarim Mohamed , Country Sales Director , Ideal Technical Solutions

The Correct answer Option C - This case need Negotiation and Influencing Skills to get all requirements and needs for the project in order to commence the Costruction Works.

Muhammad Farooq
par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

The correct answer is ---  C. Negotiation and influencing skills

Prashan Muthugala
par Prashan Muthugala , Senior Manager - Finance , Kelsey Developments PLC

Negotiation and influencing skills

MICHAIL KOSTOUROS  PMP PMI-RMP
par MICHAIL KOSTOUROS PMP PMI-RMP , Project Manager , SEEC S.A.

MOST OF THE TIME MANAGER IN ORDER TO KEEP ON TRACK THE PROJECT PLAN USES THE NEGOTIATION AND INFLUENCE SKILLS SO AS TO OBTAIN AND BIND THE BEST RESOURCES , SO THE BEST ANSWER FOR THIS QUESTION IS (C). 

Zaferullah Sharief, PMP®
par Zaferullah Sharief, PMP® , Project Manager , Huawei Technologies

Option C is the best choice.

All skills mentioned and much more are mandatory for this kind of project in such a resource crunch situation but it also gives opportunities to people involved to enhance their skill sets. In my opinion the most suitable skill is c negotiation and influencing skill however no other can be undermined.

Option (C) Negotiation and influencing skills ----------

hisham abu dagga
par hisham abu dagga , Project Manager / مدير مشاريع , مؤسسة عبدالكريم العواض للمقاولات

Thank you for the invitation

Option C

With greetings and appreciation

Gourab Mitra
par Gourab Mitra , Manager IT Project Program and Delivery Management(Full Time Contract/Consulting Role) , IXTEL(ixtel.com)

Correct answer should be C

يوسف دمدوم
par يوسف دمدوم , مهندس و مسير , مقاولة اشغال البناء

Thank you for the invitation

I agree the option C