You are the project manger for Xylophone Phonics. It produces children's software programs that teach basic reading and math skills?

You are performing the Quality Planning process and are identifying nonproductive activities. Part of this involves capturing information such as process boundaries, process configurations, and process metrics. Which of the following does this describe?

A. The process improvement plan

B. The quality management plan

C. The cost of quality

 D. The quality metrics

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2017/05/26
Aneesh Shandilya
par Aneesh Shandilya , Manager/ Lead Electrical , Orpic

A. The process improvement plan is the correct answer.

Zaferullah Sharief, PMP®
par Zaferullah Sharief, PMP® , Project Manager , Huawei Technologies

Option B is the correct answer