Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.
You are performing the Quality Planning process and are identifying nonproductive activities. Part of this involves capturing information such as process boundaries, process configurations, and process metrics. Which of the following does this describe?
A. The process improvement plan
B. The quality management plan
C. The cost of quality
D. The quality metrics
A. The process improvement plan
A. The process improvement plan is the correct answer.
Option B is the correct answer