Communiquez avec les autres et partagez vos connaissances professionnelles

Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.

Suivre

During development of schedule in Primavera P6, what will you prefer to develop the schedule through, the WBS or Coding?

user-image
Question ajoutée par ZULFIQAR ALI , Planning/ Project Control Manager , King Abdullah University Of Science And Technology
Date de publication: 2017/06/05
ZULFIQAR ALI
par ZULFIQAR ALI , Project Controls Manager , Nakheel Dubai

WBS is more used now a days as compared to activity coditing strucutre.

Ahmed Mohamed Abdel Kader Al-Assar
par Ahmed Mohamed Abdel Kader Al-Assar , Project Control Engineer , QU

Work breakdown structure is more detailed to organize the scope of works and its needs

I will prefer WBS while development of schedule in P6. Activity coding can be used for organizing the schedule.

Earlier using P3 it was very difficult to use WBS and if you wanted to make changes it was a disaster. But now in P6 WBS is more easy and flexible. The best way to go in P6 is WBS, in my opinion.

Binil Paul
par Binil Paul , Senior Planning Engineer , Keo International Consultants - Qatar

WBS is the easiest to build 

but if you combine it with Activity codes , then your schedule is more powerful in reporting 

hence a combination is the best option

More Questions Like This

Avez-vous besoin d'aide pour créer un CV ayant les mots-clés recherchés par les employeurs?