During development of schedule in Primavera P6, what will you prefer to develop schedule though the WBS or Coding?

user-image
Question added by ZULFIQAR ALI , Planning/ Project Control Manager , King Abdullah University Of Science And Technology
Date Posted: 2017/06/05
ZULFIQAR ALI
by ZULFIQAR ALI , Planning/ Project Control Manager , King Abdullah University Of Science And Technology

I fully agree with friends that WBS is perfered as compared to activity coding in Primavera. Activity coding help to organize the project as required

ZULFIQAR ALI
by ZULFIQAR ALI , Project Controls Manager , Nakheel Dubai

In Primavera P6, mostly all planners work on WBS. In P3 it was Activity coding