Working on EVM what mistakes mostly project controls professionals are doing?

user-image
Question added by ZULFIQAR ALI , Planning/ Project Control Manager , King Abdullah University Of Science And Technology
Date Posted: 2017/06/06
Zulfiqar Ali Abro
by Zulfiqar Ali Abro , Planning Manager , Enbridge Inc

As a project controls professional, one of the most important things to understand is that there are a huge number of different formulas that can make your life significantly easier on a daily basis.

·       EV = BAC x % Complete

·       SV = EV – PV ·       CV = EV – AC ·       SPI = EV / PV ·       CPI = EV / AC ·       EAC = BAC / CPI

 

·       ETC = EAC – AC