You have summarized the project and note that 28,000 hours have been scheduled, 25,000 hours have been earned and 26,000 hours paid?

The correct conclusion is:

A. The project is operating at a favorable cost efficiency ratio.

B. the project is spending more than planned

C. the project is behind schedule

D. the project is ahead of schedule

E. B and C

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2017/06/11
Krishna   KHASANIS  PMP
par Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

I will go with option C - the project is behind schedule as shown by ZULFIQAR ALI and thanks for the invite. 

ZULFIQAR ALI
par ZULFIQAR ALI , Planning/ Project Control Manager , King Abdullah University Of Science And Technology

SPI = EV/PV = 25000/28000 = 0.89. If SPI is less then 1 means project is behind the schedule.

My answer is C. the project is behind the schedule.

Muhammad Farooq
par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

C. the project is behind schedule

Reference:  Here, EV=25, PV=28 and AC=26; so CV = -1, SV = -3 and CPI = 0.96 and SPI = 0.89. Therefore it is over budget and behind schedule; but over-budget by very insignificant point, while it is certainly  behind schedule by over 10%. That's why answer is C.