A. Linear responsibility charts.
B. Scope baseline.
C. Job descriptions.
D. Organization of project.
E. Policies and procedures.
It is very tricky question; scope baseline is component of management plan.
The project management plan is a collection of baselines and subsidiary plans. The plan includes:
Baselines for : Scope, Schedule, Cost
Management Plans for : Scope, Schedule, Cost, Quality, Human Resources,
Communications, Risk and Procurement.
My answer is C. Job Description
My answer is option C - Job Description.
In my opinion - B. Scope baseline.
C. Job descriptions ----------------------
I think it is the project team that is responsible for producing the Scope Baseline after getting the inputs from customer & stakeholders. Hence, in my opinion B-Scope baseline is the exception & thanks for the invite.
C. Job DescriptionDepends on the plant and requirement scope baseline can be excluded.