Your project's primary constraint is quality. To make certain the project team members don't feel too pressed for time and to avoid schedule risk?

you decide to use which of the following activity estimating tools?

A. Quantitatively based durations

B. Analogous estimating

C. Reserve analysis

D. Expert judgment

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2017/06/11
Sam Oboh
par Sam Oboh , Principal, Architecture , Inspirarqx | Kasian, Edmonton, Canada

Expert judgement always work best in dealing with qualitative challenges...

Robert Malak
par Robert Malak , Projects Manager , Ankido Oil Services for General Contracts DMCC

I would use Reserve analysis to avoid schedule risk and to ease the time pressure from the project team members.

 

Lahoucine Khabid
par Lahoucine Khabid , Lecturer , Cadi Ayyad University

It's a dual act for reserve analysis through expert judgement

Ali Farhan Syed
par Ali Farhan Syed , Office Incharge (Student Section) , University of Health Sciences, Lahore

I dont care about the methods.

Quality and Employees both are important

Erwin Cataniag
par Erwin Cataniag , Admin Secretary / Document Clerk , SISCO

A. Quantitatively based durations

Krishna   KHASANIS  PMP
par Krishna KHASANIS PMP , Project Manager-Electrical , Larsen & Toubro Ltd, P T & D (International)

To avoid schedule risk , option C - reserve analysis is used along with other tools for estimating the activity durations & thanks for the invite. 

Tabusam Nasreen
par Tabusam Nasreen , Teacher , Glassgow public school mananwala

option D is right. Expert judgement

Avinash  Rebello
par Avinash Rebello , MEP Engineer , Integrated Electronics and Electromechanical LLC

Expert judgment is a better option.

يوسف دمدوم
par يوسف دمدوم , مهندس و مسير , مقاولة اشغال البناء

I agree the option C Analogous estimating

More Questions Like This