Communiquez avec les autres et partagez vos connaissances professionnelles

Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.

Suivre

Early activities are detailed and future activities are still at a high level is called?

 

A. scope verification

B. progressive elaboration

C. stratagic elaboration

D. stratagic planning

 

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2017/06/17
MICHAIL KOSTOUROS  PMP PMI-RMP
par MICHAIL KOSTOUROS PMP PMI-RMP , Project Manager , SEEC S.A.

The B answer is the correct , it describes the situation when we cannot determine the detail scope of all phases in a unique and complex project but only the next phase each  time

More Questions Like This