How much time it takes to approve a shop drawing?

user-image
Question ajoutée par Sunil Kumar , Document Controller , Feedback Infra Pvt. Ltd.
Date de publication: 2017/07/01
Hafiz Muhammad Rizwan hameed
par Hafiz Muhammad Rizwan hameed , Senior Structural Design Engineer , Associated Consulting Engineers Pvt Ltd.

Usually this time is mention in the contract decoumnets. In my project (Neelum Jhelum Hydropower Project) it is 21 days.

Qaiyyum shaik
par Qaiyyum shaik , Draughtsman Electrical , Sharqawi MEP Contractors

IT DEPENDS ON CONTRACT WITH CLIENT OR CONSULTANT OUR PROJECTS HAVE 14 DAYS 

Chantal EL Saliby
par Chantal EL Saliby , Project Manager , NOORCO

General:

Contractor must submit schedule of submittals within 60 days of the Contract start.

Schedule submitted to Shop Drawing Review Office and EOR.

Submittals should not occur before schedule submittal.

Shop Drawing submittal schedule to allow 45-day review time.

Time commences upon EOR’s receipt.

Time ends upon EOR’s submittal

 

Aneesh Kamalasanan
par Aneesh Kamalasanan , Draughtsman , Multiplex LLc.(Brookfield Multiplex)

Generally civil shop drawings take 2-3 days at each level, if there no changes required from the end-user. that is 6-10 days for each drawing. If there are bunch of drawings related to each other, the overall time taken for approval will be reduced.

Ahmed Khamees
par Ahmed Khamees , Team Leader - Facade Design , Sobha facades

15 days max starting rom the day recieved.

Hassan Mayahi
par Hassan Mayahi , SENIOR STRUCTURAL ENGINEER , CHINA STATE ENGINEERING

Based on Planned scheduel and Contract,

from 2  to 15 days ...

Dominic Sagar
par Dominic Sagar , Project manager , Nakhsha Builders

Generally, shop drawings are scrutinized at different levels, Namely,

First by the supplier/ contractor himself.

Second by the consultant,

Third by the End-user/ Client.

The time taken depends on the complexity of the drawings.

Generally civil shop drawings take 2-3 days at each level, if there no changes required from the end-user. that is 6-10 days for each drawing. If there are bunch of drawings related to each other, the overall time taken for approval will be reduced.

ziahasan syed
par ziahasan syed , Sr.Mechanical Engineer (Technical Dept) , AZMEEL CONSTRUCTION COMPANY

with in the planned schedule date and Based on final Architectural or Infra approved drawings mechanical and electrical utilities will be coordinate to approved shop drawings with in a week. 

AFAQ HUSSAIN
par AFAQ HUSSAIN , DESIGN MODULER , SAUDI BINLADIN GROUP OF COMPANY

MAXIMUM TWO WEEKS FOR FIRST APPROVAL BUT SHULD BE AVABILITY ALL DESING INFORMATION.

MINIMUM ONE WEEK FOR 2ND APPROVAL

Mohamed Faried Radwan
par Mohamed Faried Radwan , مهندس/مهندسه مكتب فنى , أبناء حسن علام

The time between the date recieved and the aprroval date is always will be mentioned in the conratct and it usually be from 7-21 days for the first submittal  and 7 days for the second revision  

Imam Husain
par Imam Husain , HVAC Foreman , Saudi Kayan Petrochemical Company

Depends on Contractor with clients