How is manpower resource availability set up in a staggered rotational employees for offshore scheduling for plant maintenance?

In Maximo or Viziya scheduler, resource availability is setup using labor calendar, shift and cycle start. But it is a complicate process to establish availability by craft and by people. How is it managed in other industries.

user-image
Question ajoutée par Panneer Arthanari , CMMS ENGINEER, ASSET MANAGEMENT SPECIALIST , ABUDHABI MARINE OPERATING COMPANY
Date de publication: 2017/07/03