recovery program is used when our project is delayed and we are trying to improve our projected completion date on the schedule; it could inclode but not limited to corrective action which have mitigatory effact
mitigation on the other hand is rdusing the difference usule done in risky projects by adding risk respones plan
revised program is doing changes to our schedule (that doesn't mean that our plan is incorrect) it could be seen as an update for the plan done when needed