Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.
Steps:
1. Add Resource
2. Assign Resource to the activity.
3. Put Budgeted quantities.
4. The cost will be calculated with the price/unit assigned to the resource.(Cost = Budgeted Quantity * Price/Unit)