Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.
Option (A) -------------------
Option A is the correct answer.
Answer: A
Explanation:
The Initiating process is where stakeholders have the greatest ability to influence outcomes of the project. Risk is highest during this stage because of the high degree of unknown factors.