Assume that you have a network where an activity on the critical path can be crashed by two weeks. If the activity is actually crashed by two?

weeks, then:

A. A new critical path may appear after the crash.

B. All of the other alternatives apply.

C. The available slack on the noncritical paths will increase.

D. Both1) The project's schedule will be reduced by2 weeks and2) The available slack on the

noncritical paths will increase.

E. The project's schedule will be reduced by2 weeks.

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2017/07/28
Binil Paul
par Binil Paul , Sr. Planning Engineer , KEO International Consultants

Option A might be possible.

and Option E if Option A doesn't happen

Falah Almutlaq
par Falah Almutlaq , مدير مالي , جمعية شآبيب الخيرية لذوي الأحتياجات الخاصة

A. A new critical path may appear after the crash

Both1) The project's schedule will be reduced by2 weeks and2) The available slack on the

Muhammad Farooq
par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Option A -------------------