Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.
weeks, then:
A. A new critical path may appear after the crash.
B. All of the other alternatives apply.
C. The available slack on the noncritical paths will increase.
D. Both1) The project's schedule will be reduced by2 weeks and2) The available slack on the
noncritical paths will increase.
E. The project's schedule will be reduced by2 weeks.
Option A might be possible.
and Option E if Option A doesn't happen
A. A new critical path may appear after the crash
Both1) The project's schedule will be reduced by2 weeks and2) The available slack on the
Option A -------------------