is in execution phase. Which statement is TRUE about the project?
A. requirement added later therefore project is running late
B. temporary project
C. key resource has left the organization therefore running late
D. limited license of development environment therefore running late
According to me Answer is A, as other options can be managed and achieved, whereas if additional scope is added to the actual contract and amendment contract is signed then need to revise the implementation plan and execution so it will change project completion date.
limited license of development environment therefore running late
I would select answer A.
In my opinion all of the other answers are not quite suited to answer by the Project Manager. Specially answer C is not suited at all as resource management or resource allocation is PM's responsibility and this matter wouldn't be a major issue for extending the project by another year. However, if the issue was an unavoidable, then all stakeholders should approve the extension.
If your project is 2 year late in 1 year project some one has a serious problem. Time is money somebody has to pay.
Answer: B
Explanation: Project is continuing to expand means it is temporary project.
Other options can be achievable to complete the project if it is important for organization.