Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.
approved corrective action and an update to the project management plan. Which process does this describe?
A. Information Distribution
B. Manage Project Team
C. Manage Stakeholders
D. Performance Reporting
Answer is C-Manage Stakeholders
Answer: C
Explanation:
The two clues in this question are the face-to-face meetings (a communication method) and the resolved issues, which is an output of the Manage Stakeholders process.