Who is responsible to publish project charter?

A. project sponsor

B. team lead

C. a manager external to the project.

D. project manager

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2017/08/05
Muhammad Farooq
par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: C

Explanation:

Based on PMBOK, the project charter should be published by a manager external to the project but with sufficient power and authority.