Which is not a part of the project cost baseline but is included in the project budget?

A. Management Overheads

B. Activity Cost Contingency Reserve

C. Project Management Planing

D. Management Contingency Reserve

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2017/08/11
Muhammad Farooq
par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: D

Explanation: The difference between the Cost Baseline and Funding requirement at Project completion is Management Contingency Reserve. Management Contingency Reserve is not part of project cost baseline.