What are the first three things you’d do if you join QA/QC/HSE?

user-image
Question ajoutée par Utilisateur supprimé
Date de publication: 2017/08/25
Murugesh Sambasadhasivam
par Murugesh Sambasadhasivam , Operations Manager , Fortune

The first and foremost thing is to see the Track record ( HSE - No of Manhours worked safely and QA/QC the NCRs and the actions taken ). 

The second thing would be to look at the QHSE Policy Document ( Look for glaring loop holes or mistakes ) and the QHSE organizational structure - the team - The leads, the auditors etc. 

The third thing is to understand the culture of the organization ( how the QHSE Policy is being accepted and implemented ) You need to walk around and talk to employees and this will give a better understanding. 

Joaquin  Medina
par Joaquin Medina , Project Manager (Construction, Planing and Quality) , Sodralca

The man hours worked or for work, if if we have a new contract, The quality control plan or policy, and the support from the owner for quality control department

Mazen Amad
par Mazen Amad , QA/QC Manager , CCC, BACS Riyadh Metro Project (Bechtel, Almabani, CCC and Siemens Consortium)

  • Understand the company QA/QC/HSE Policy.
  • Create and improve QA/QC/HSE Policy awareness within the organization;
  • Identify areas for improvements and uodate the  company QA/QC/HSE plan.

Abbas Sadiq
par Abbas Sadiq , QA Lead , Micad Systems

Analyse the Current state

Gap analysis based on business needs and QA recommendations

Fill the Gap using company's Standard operating procedures

Unnikrishnan K Vidyadharan
par Unnikrishnan K Vidyadharan , QA/QC engineer , Shapoorji Pallonji Mideast LLC

1. Understanding the company QHSE policy.

2. To go through the PQP.

3. Read the Specs.

Jawad  Ali
par Jawad Ali , QA/QC Inspector Civil Architecture , Salini Saudi Arabia

As A QC first three things I have to do would be non other than the specification , standards and PQP .

Sujieth Tom Alex
par Sujieth Tom Alex , Internee , Hindustan Aeronautical Ltd.(HAL) - Helicopter MRO

  1. Perform all daily inspection and test of the scope and character necessary to achieve the quality of construction required in the drawings and specifications for all works under the contract performed ON or OFF site.
  2. Cary out inspection and checking for all quality related procedures in the site and ensures activity at the site are as per approved method statement and inspection test plan.
  3. Report to the QA/QC Manager, control, and monitor all activities related to Quality Management System, QMS.

Dorna Ghotb
par Dorna Ghotb , internal manager , QA TECHNIC

Run programs to teach safety tips to employees of different departments

Rajat Singh Rajput
par Rajat Singh Rajput , Test analyst , Cognizant Technology Solutions

1st Understand company policies and adhere to it.

2st Read application Information and workaround documents. To understand the best way or practice to start and complete task. 

3rd On time delivery of application build without any bug and maintain all workaround documents as per build release.

PANDIYARAJAN JAYARAMAN
par PANDIYARAJAN JAYARAMAN , Sr. Engineer QA/QC , L&T Delma Mafraq JV

1. First, have to go through the Contract Documents such as Contract Terms and condition, specification, Soil Investigation report, Contract drawing, the scope of works and statutory requirements.

2.  preparation of Project Quality Plan according to Project requirements and ISO10005:2005.

3. Conduct Induction training on Approved Project Quality Plan.

Vladimir Galenco
par Vladimir Galenco , Drilling Supervisor , Saudi Aramco

  • Read the documentation
  • Explore the system bit by bit/if you don't have one you have to do it 
  • Understand the stage the project is in