In the initiation phase, project manager has been assigned to the project which process that must occur after this?

A. Develop the project charter

B. Develop the preliminary project scope statement

C. Collect Requirements

D. Develop the project statement of work

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2017/08/26
Muhammad Farooq
par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: C

Explanation:

< li >After the project manager assigned to a project, Collect Requirements is started.

< li >Develop the project charter is before all of this.