What is the main difference between the project charter and the preliminary scope statement?

A. Audience of the project charter is the stakeholders and Audience of the preliminary scope statement is the project team.

B. project charter is created in initiation phase and preliminary scope statement is created in execution phase

C. The purpose of the preliminary scope statement is to authorize the project and The purpose of the charter is to describe the project.

D. project charter and the preliminary scope statement is same document with different name 

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2017/09/10
Minhajul Islam
par Minhajul Islam , Sr. Computer Programmer

A-

Project Charter is the most initial phaze of project and stackholders involved in it. When say yes and go then next phase start to generate Scope Statement with the Team Members and Planning Team and here Out of the project defined.

 

Annabel Ekwere-Shallum
par Annabel Ekwere-Shallum , Process Design Engineer , Mobil Producing Nigeria Unlimited

 A - Audience of the project charter is the stakeholders and Audience of the preliminary scope statement is the project team.

andre andre
par andre andre , On Site Sitemanager/Structural /Civil/Mechanical/Tank plate Erection. , Kanye Kanye Projects Africa.

C -The purpose of the prelimanary scope statement is to autherize the project and the purpose of the charter is to redescribe the project.

SRINIVAS MANI
par SRINIVAS MANI , Business Consultant , Southern Electronics Pvt Ltd

A Project Charter is prepared for the shareholders while Preliminary Scope Agreement is for project team

Muhammad Farooq
par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: A

Explanation: < li >project charter: The purpose of the project charter is to authorize the project, and the audience are the stakeholders.

< li >preliminary scope statement: The purpose of the preliminary scope statement is to describe the project, and its audience is the project team