par Jalal Hussein Ali Musa Al'omari , Civil Engineer , Local Office

I agree with specialists answers

Moatafaaddin Zohrabzadeh
par Moatafaaddin Zohrabzadeh , project manager head , omran eskan sepahan

its depend on dia of bar used in concrete for example the weight of steel of one meter rod having six mm dia is two hundrerd and twenty grams and ten mm dia is six hundrerd and twenty grams etc you can find weight of different bars having different diameters by this formula = (d*d)/one hundrerd sixty two

Jawaid Amjad
par Jawaid Amjad , Resident Engineer , CDM Smith Inc.

Percentage of steel being used for the concrete slab is between 0.6 to 1.2 %.

Nelio Beleo
par Nelio Beleo , Civil Inspector , Petrojet

It depends on the steel requirement on the designed structure but steel ratio commonly used on columns are from 2 to 3 %, on slab are 0.5 to 1.5 % and beams are 1 to 1.5 %.

Muhammad Idrees Khan
par Muhammad Idrees Khan , Site engineer , Bin Abed Al Kaabi gen. cont.

its depends on the structural member.in slab it is likely to be 2 to 3 percent.