A. the development of schedule alternatives and work-around
B. an assessment of project shut-down liabilities.
C. the management of a contingency budget
D. The development of a contingency allowance determined by combining (layering) various estimate segments to form larger estimate segments.
E. Both1) The development of a contingency allowance determined by combining (layering) various estimate segments to form larger estimate segments, and2) the management of a contingency budget
D. The development of a contingency allowance determined by combining (layering) various estimate segments to form larger estimate segments.