Communiquez avec les autres et partagez vos connaissances professionnelles

Inscrivez-vous ou connectez-vous pour rejoindre votre communauté professionnelle.

Suivre

You are the project manager for Design Your Web Site, Inc. Your company is designing the website for a national grocery store chain. You have?

your activity list in hand and are ready to diagram the activity dependencies using the PDM technique. Which of the following statements is true?

A. PDM is also the AOA diagramming method.

B. PDM is also the AON diagramming method.

C. PDM is also the AND diagramming method.

D. PDM is also the ADM diagramming method

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2017/09/30
Muhammad Farooq
par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: B

Explanation:

The precedence diagramming method is also known as the activity on node (AON) diagramming method.

Avez-vous besoin d'aide pour créer un CV ayant les mots-clés recherchés par les employeurs?