All of the following are outputs of the Integrated Change Control process except for which one?

A. Validated defect repair

B. Approved corrective actions

C. Requested changes

D. Project scope statement updates

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2017/09/30
Muhammad Farooq
par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

Answer: C

Explanation:

Approved change requests are an output of this process, not requested change requests. The other tools and techniques of this process are rejected change requests, project management plan updates, approved preventive actions, approved defect repair, and deliverables