A. Project SOW, enterprise environment factors, and organizational process assets
B. Project SOW, enterprise environment factors, organizational process assets, project selection methods, and expert judgment
C. Project SOW, enterprise environment factors, organizational process assets, project management methodology, PMIS, and expert judgment
D. Enterprise environment factors, organizational process assets, PMIS, and expert judgment
Answer: C
Explanation:
The Develop Project Charter and Preliminary Scope Statement processes both have the following as inputs: project SOW, enterprise environment factors, and organizational process assets. Both processes share the following tools and techniques: project management methodology, PMIS, and expert judgment.