Upon completion of 75% of the project, the original schedules and cost estimates that were submitted at the inception of the project are?

referred to as the:

A. Budgeted costs.

B. Estimates upon completion costs

C. Baseline costs

D. None of the other alternatives apply

E. Scheduled costs

user-image
Question ajoutée par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.
Date de publication: 2017/10/06
Muhammad Farooq
par Muhammad Farooq , QA-QC MANAGER , AL Bawani contracting co.

C. Baseline costs --------------------------------------